title: "Video: among the turbines of Rampion, the offshore wind farm off the Sussex coast"
canonical: "https://rawy.si/preview/7074b704-95a5-4a23-afda-a998e0223da5/article/video-rampion-offshore-wind-farm-from-the-water"
url: "https://rawy.si/preview/7074b704-95a5-4a23-afda-a998e0223da5/article/video-rampion-offshore-wind-farm-from-the-water"
author: "The Quarter & Ledger desk"
author_url: "https://rawy.si/preview/7074b704-95a5-4a23-afda-a998e0223da5/author/quarter-ledger-desk"
published: 2026-09-29T05:48:11.467Z
modified: 2026-10-03T23:17:31.499Z
section: "Video"
tags: ["Video"]
language: en
license: "© Quarter & Ledger. All rights reserved. Quotation of short passages with attribution and a link to the source is permitted."
---

# Video: among the turbines of Rampion, the offshore wind farm off the Sussex coast

*A public-domain clip filmed from a boat in July 2023, and what the wind farm's own documents say*

> Twenty seconds among the turbines of Rampion, the first offshore wind farm off England's south coast, filmed from a dive boat and released without restriction. What the clip shows, how the wind farm was built and paid for, and how it sells its electricity.

## Key points

- The clip was filmed inside the Rampion Offshore Wind Farm on 9 July 2023 by Andy Li and released under the CC0 dedication.
- Rampion has 116 Vestas turbines of 3.45 megawatts each, a combined 400 megawatts, about 13 kilometres off the Sussex coast.
- Developed by E.ON and built between 2016 and 2018, Rampion was the first offshore wind farm off England's south coast.
- Rampion's Contract for Difference guarantees a fixed price per megawatt-hour for fifteen years.
- Rampion 2 received development consent in April 2025 for up to 90 further turbines.

![Video: among the turbines of Rampion, the offshore wind farm off the Sussex coast](https://rawy.si/uploads/7074b704-95a5-4a23-afda-a998e0223da5/images/photo-rampion-wind.jpg)

The clip was filmed from a boat inside the **Rampion Offshore Wind Farm** on 9 July 2023 by Andy Li, who released it under the CC0 dedication, which places it in the public domain. The camera passes among the turbine towers, each on a steel monopile driven into the seabed, with the blades turning in a moderate wind.

The file's description records that it was taken on a dive trip; the wind farm lies about 13 kilometres off the coast between Brighton and Worthing and is visible from the shore on a clear day.

## What you are looking at

Rampion has **116 turbines** with a combined capacity of 400 megawatts, according to the wind farm's own published description and the Crown Estate's register of offshore projects. Each turbine is a Vestas machine of 3.45 megawatts; the electricity is collected by [cables on the seabed](/article/sector-in-a-page-copper-mining) to an offshore substation, seen in some of the photographer's other pictures as a yellow platform, and brought ashore at Brooklands in Worthing to a substation near Bolney. The wind farm was developed by E.ON, built between 2016 and 2018, and is now owned by RWE with partners; it was the first offshore wind farm off the south coast of England.

## How was the wind farm paid for?

Rampion was awarded a **Contract for Difference** by the UK government under the 2014 scheme's early allocation, which guarantees a fixed price per megawatt-hour for fifteen years: when the market price is below the strike price the generator is topped up by a levy on electricity bills, and when it is above, the generator pays back the difference. The Low Carbon Contracts Company, which administers the contracts, publishes the strike price of every project in its register. The Crown Estate, which owns the seabed, receives a lease payment.

## What comes next

A second project, Rampion 2, received development consent from the Secretary of State in April 2025 for up to 90 further turbines, according to the Planning Inspectorate's decision record. Offshore wind supplied about 17 per cent of [Britain's electricity](/article/how-an-electricity-grid-stays-balanced-second-by-second) in 2024 by the figures in the Department for Energy Security and Net Zero's Energy Trends, and the turbines in the clip are a small part of that total, but they are the part a visitor to Brighton can see.

## Frequently asked questions

### How big is the Rampion wind farm?

Rampion has 116 turbines with a combined capacity of 400 megawatts, according to the wind farm's own description and the Crown Estate. Each is a Vestas machine of 3.45 megawatts, and the farm lies about 13 kilometres off the coast between Brighton and Worthing.

### How does a Contract for Difference work?

It guarantees the generator a fixed price per megawatt-hour, for fifteen years in Rampion's case. When the market price is below the strike price the generator is topped up by a levy on electricity bills; when it is above, the generator pays back the difference.

### Is Rampion being expanded?

A second project, Rampion 2, received development consent from the Secretary of State in April 2025 for up to 90 further turbines, according to the Planning Inspectorate's decision record.

## Sources

- [File:Rampion Wind Farm 2023-07-09 162428.webm (CC0)](https://commons.wikimedia.org/wiki/File:Rampion_Wind_Farm_2023-07-09_162428.webm) — Wikimedia Commons
- [Key facts](https://www.rampionoffshore.com/wind-farm/key-facts/) — Rampion Offshore Wind
- [Offshore Wind Report 2025](https://www.thecrownestate.co.uk/our-business/marine/offshore-wind-report-2025) — The Crown Estate
- [Contracts for Difference schemes register](https://register.lowcarboncontracts.uk/) — Low Carbon Contracts Company
- [Rampion 2 Offshore Wind Farm: project information and decision](https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010117) — Planning Inspectorate
- [Energy Trends: UK renewables](https://www.gov.uk/government/statistics/energy-trends-section-6-renewables) — Department for Energy Security and Net Zero, GOV.UK